Home
Board of Supervisors
Planning Commission

Agendas
Announcements
Committees
Forms
Minutes
Ordinances
Public Notices
Resident's Guide
Road Department
Township History

Township News
Zoning & Subdivisions
Zoning Hearing Board

Emergency Resources

Municipal Office

589 Lake Warren Road
PO Box 100
Ferndale PA 18921
Phone: 610.847.5058
FAX: 610.847.5812

Road Department: 610.847.2727
Zoning & Building: 610.847.8440

Email

  • EMERGENCY: 911
  • STATE POLICE -
    NON-EMERGENCY:
    215.249.9191

610.847.0911
Directly to Dublin Barracks

YOU NEED A PERMIT IN NOCKAMIXON

PennDot Route 32 Update

River Road to reopen this week
 phillyBurbs.com - Philadelphia,PA,USA
 Crews are working on a portion of the road in Nockamixon between Route 611 and Narrows Hill Road that was damaged in the same 2005 flood

District 6 Traffic Bulletin

Location

Bucks County

Street(s)

*PA 32 (River Rd.), Nockamixon Twp.

Restriction

Road Reconstruction: CLOSED & DETOURED between PA 611 & Narrows Hill Rd. DETOUR POSTED.

Date

4/21/08-10/08

Contractor

Blooming Glen

Cost

$6.5 million

 

Route 32 (River Road) Construction Schedule

July 11, 2008

 

Route 32 (FL 6) between Green Hill Road and Route 263 in Solebury Township.

 

  • Contractor is currently installating a 1,800-foot concrete retaining wall.  The project also calls for installing new guide rail, installing six storm water inlets and drainage pipes, and installing a clay liner along the sides and bottom the Delaware Canal.

 

  • Excavating on July 17 through July 19.  
  • Backfill anchor block July 15 and July 16.  
  • Install geo stone and backfill July 12 and July 14-15.  
  • Canal restoration July 14-18  
  • Install anchor block July 14-19.  
  • The contractor will also be addressing storm water issue along the project area.

 

Preliminary construction began November 26

 

Route 32 will be closed and detoured to through traffic 24-hours a day beginning January 7. 

 

Contractor working seven days a week, 10-12 hour days.

No traffic will be allowed through work zone on weekends.

 

Project expected to be completed by August 1 due to the amount of rock that has to be drilled through. Local access to businesses will be maintained.Work is weather dependent. Cuttalossa Road will be closed at the intersection of Route 32. Route 32 (FL 3) between Narrows Hill Road and Route 611 in Durham and Nockamixon Township 
  • The project calls constructing a 5,000-foot long retaining wall along Route 32; reconstructing Route 32; and installing new guide rail.
 
  • Erosion and sediment control on June 9 through June 13.
 
  • Lay out piles on July 14 and July 16.
 
  • Drill piles on July 14-18.
 
  • Install Soldier Piles on July 14-18.
 
  • Install precast concrete lagging on July 14-18.
 
  • Backfill wall on July 15 and July 17.
 
  • Roadway excavation on July 14, July 16, and July 18
 Construction began April 14. Detour to began April 21. Southbound Route 32 motorists will detour over Route 611 and Marienstein Road. Northbound Route 32 motorists will continue to detour over Narrows Hill Road and Route 611. Trucks will detour over Route 611, Route 413, and Route 263/Route 202. 

The project is expected to be completed by October 31.

 

 Route 32 (FL 4) in Morrisville and New Hope boroughs, Lower Makefield, Solebury, and Bridgeton townships. This project has been completed.  

 

Get PennDOT’s local news releases, traffic bulletins and other information anytime at http://www.dot.state.pa.us/Penndot/Districts/district6.nsf/District%206-0%20Homepage?OpenFrameset. Bookmark this site and check it often!

____________________________
Charles Metzger
Community Relations Coordinator
PENNDOT
7000 Geerdes Boulevard
King of Prussia PA 19406
610.205.6801
cmetzger@state.pa.us

 

 

Route 32 (River Road) Construction Schedule JUNE 06 , 2008

Route 32 (FL 3) between Narrows Hill Road and Route 611 in Durham and
Nockamixon Township
 
*        The project calls constructing a 5,000-foot long retaining wall
along Route 32; reconstructing Route 32; and installing new guide rail.
 
*        Erosion and sediment control on June 9 through June 13.
 
*        Lay out piles on June 9 through June 13.
 
*        Drill piles on June 9 through June 13.
 
*        Install Soldier Piles on June 9 through June 13.
 
Construction began April 14.
 
Detour to began April 21.
 
Southbound Route 32 motorists will detour over Route 611 and Marienstein
Road.
 
Northbound Route 32 motorists will continue to detour over Narrows Hill
Road and Route 611.
 
Trucks will detour over Route 611, Route 413, and Route 263/Route 202.
 
The project is expected to be completed by October 31.

 

Route 32 (River Road) Construction Schedule

May 23, 2008

 

Route 32 (FL 6) between Green Hill Road and Route 263 in Solebury Township.

 

  • Contractor is currently installating a 1,800-foot concrete retaining wall.  The project also calls for installing new guide rail, installing six storm water inlets and drainage pipes, and installing a clay liner along the sides and bottom the Delaware Canal.
     
  • Pre drill piles on May 27 through May 31.
     
  • Drill piles on May 27 through May 31.
 
  • Cut and install beams on May 29 through May 31.
     
  • Place concrete panels on May 27-28.
     
  • The contractor will continue to drill holes for the retaining wall posts and installing posts Mondays through Saturdays through June 7.
     
  • The contractor will be receiving concrete panels May 27 through May 30.   
     
  • The contractor will also be addressing storm water issue along the project area.
 Preliminary construction began November 26 Route 32 will be closed and detoured to through traffic 24-hours a day beginning January 7.   

 

No traffic will be allowed through work zone on weekends.

Project expected to be completed by July 3 due to the amount of rock that has to be drilled through. Local access to businesses will be maintained.Work is weather dependent. Cuttalossa Road will be closed at the intersection of Route 32.  

 

Route 32 (FL 3) between Narrows Hill Road and Route 611 in Durham and Nockamixon Township

     
  • The project calls constructing a 5,000-foot long retaining wall along Route 32; reconstructing Route 32; and installing new guide rail.
     
  • Erosion and sediment control on May 27 through May 31.
     
  • Lay out piles on May 28.
     
  • Drill piles on May 27 through May 31.
     
  • Install Soldier Piles on May 27 through May 31.
 Construction began April 14. Detour to began April 21. 
 
 Southbound Route 32 motorists will detour over Route 611 and Marienstein Road.
 Northbound Route 32 motorists will continue to detour over Narrows Hill Road and Route 611. Trucks will detour over Route 611, Route 413, and Route 263/Route 202. The project is expected to be completed by October 31.
 

 

Route 32 (FL 4) in Morrisville and New Hope boroughs, Lower Makefield, Solebury, and Bridgeton townships.

     

  • Crews patched asphalt, paved, installed guide rail between Robinson Place and Woodside Road in Lower Makefield Township. 
This work is complete 
  • Crews stabilized embankment of the Delaware Canal, reconstructed pavement, installed guide rail between Old Ferry Road and East Trenton Avenue/Calhoun Steet in Morrisville Borough.
This work is complete 
  • Crews stabilized the embankment of the Delaware Canal between Route 232 (Windy Bush Road) and Aquetong Road in New Hope Borough and Solebury Township
This work is complete 
  • Crews restored the embankment along the Delaware Canal, installed guide rail, and reconstructed pavement between the Trail’s End Canal Bridge and the Milford Bridge in Bridgeton Township
This work is complete 
  • Crews will reconstruct a stone retaining wall near the intersection of Fleecydale Road in Solebury Township
Construction begun February 18. The project is expected to be completed by May 29. Contractor has one day of work to install rip rap along canal.  Work will be scheduled for either Wednesday or Thursday. Work is being completed under traffic with no detour.  

 

Get PennDOT’s local news releases, traffic bulletins and other information anytime at http://www.dot.state.pa.us/Penndot/Districts/district6.nsf/District%206-0%20Homepage?OpenFrameset. Bookmark this site and check it often!

__MAY 16TH, 2008 UPDATE__________________________

 

   
   
   

 

 

 

   
 
© 2008/2009 Nockamixon Township.
All Rights Reserved.
If you can't find what you are looking for or... to report a broken link
Email WebMaster